Hi All,
We are creating a BPM in PI7.31 single stack EHP1, such that it splits one message in to Multiple messages we face issues in the send activity.
Steps Followed:
1. Created Interface Mapping in ESR with the required mappings with 1:M scenario.
2. Imported the Operation Mapping from the ESR in to ProcessModeling(NWDS)
3. Created Automated Activity and assigned Operation Mapping which provides multiple messages to the next activity.
4. Set the property of the next Send Activity, as Par For Each
When we test the scenario in runtime, the mapping step executes fine.
The 4th Step that is the Send Activity executes according to the number of messages, but the output of the message contains only the content of the first message for all the messages.
Eg: If there are 4 outcomes of this mapping, all the four message contains the first message content.
Please suggest the steps to make it work.